3 x 5.000 m3 tank erection, Fertigent BVBA, Gent
NDT of refinery technological equipment and pipelines, Mažeikiai
FOSTER WHEELER IBERIA S.A. FCC GASOLINE SHU PROJECT at refinery, Mažeikiai
Turnover of KR-101, LK-2 unit at refinery, Mažeikiai
2005
2004
2015
Turnover of KR-101, LK-2 unit at refinery, Mažeikiai
Project:
Turnover of KR-101, LK-2 unit at refinery.
Services:
RRT – 900 exposures, PT – 180 pipe welds, PMI – 400 pcs.
Place, project start – finish:
Mažeikiai, Lithuania;
2006 June – 2006 September.