Project:

  • Turnaround 2009; Pipeline diagnostics, thickness measurements of refinery pressure vessels and pipelines.

Services:

  • RT – 2200 expositions, UT – 670 pipe welds, MT – 320 pipe welds, PT – 600 pipe welds, HT – 2000, PMI – 700, PWHT – 660 pipe welds, UT thickness measurements – 20000; UT thickness measurements – 105000, gamma ray thickness measurements – 3050.

Place, project start – finish:

  • Mažeikiai, Lithuania;
  • January  2009 – December  2009.